Kilternan Parish Church

Project Name

KILTERNAN PARISH CHURCH

Location

KILTERNAN

Main Contractor

ABM

Date

SEPTEMBER 2018

SUMMARY

SGW have been contracted to carry out the demolition and ground works packages for the construction of a new Parish Hall in Kilternan for Main contractor ABM. The first stage of the works consisted of the full demolition of 3 no. Structures, one of which was ajoining a 180 year old listed building, which was completed without a hitch. The listed building was then stripped back to shell and core for renovation.

Due to the site conditions it was determined that a soil retaining structure was required and SGW were instrumental in determining the most cost and time effictive solution as being a ‘king post’ retaining wall, poured against the existing bank. The wall was completed in a safe and timely fashion, with no disturbance to the ground behind, allowing the construction of the of the main build to start.

 